Whittier Area Community Church, Whittier, CA
Project
This church expansion project was completed in 2010. The site is approximately 17 acres. The site exhibits a terrain that reached almost 80 foot of vertical difference across the site; therefore the site design consisted of several retaining walls of varying heights. Adkan was there from the beginning, including obtaining project entitlements, organizing community meetings and designing/phasing the project such that church activities could remain on-site during construction. The project grading activities moved close to 100,000 CY of material to complete the project and included approximately 2,200 Lineal feet of retaining wall, ranging in height from 2-feet to 10-feet.
Services Performed
- Entitlements/Community Meetings
- Boundary And Topographic Survey
- Engineering Plan Preparation
- Retaining Wall Design
- SUSMP Design
- Construction Staking
Client
Grant general Contractors/Whittier Area Community Church